The prototype of the Qianjiangyuan General Airport in Quzhou

During the National Day holiday, the construction site of the Qianjiangyuan General Airport project was very busy, with more than 100 people participating in the construction every day. At present, 92% of the earthwork filling of the main project has been completed, the foundation compaction construction has been completed, the piling and foundation of the main structure of the terminal have been completed, and the access road is ready for traffic.